Con-Tec Solutions
80-bay EV charging infrastructure for logistics hub
EV & SolarLogistics operator

80-bay EV charging infrastructure for logistics hub

80 charge pointsSmart managementDNO liaison
Charge points installed

80

80 smart EV charge points across a multi-acre logistics depot, connected to a central load management platform.

Reinforced grid capacity

5MW

New HV transformer and LV distribution network installed under a DNO Section 16 contestable works agreement.

Fleet coverage

100%

Full fleet coverage achieved — every vehicle guaranteed charged by start of shift under the smart load management schedule.

The Brief

A major logistics operator required 80 smart EV charge points across a multi-acre depot site to electrify its vehicle fleet — with DNO application, grid reinforcement and a load management system that could handle overnight bulk charging without triggering demand penalty charges.

Grid Reinforcement and DNO Liaison

The existing site supply was insufficient for the additional load. Con-Tec managed the full DNO application process — including load flow modelling, protection coordination and the formal Section 16 contestable works — and oversaw the new HV transformer and associated LV distribution network from design through to energisation.

On-site generation and grid integration supporting the EV charging scheme
Smart EV charge points installed at a logistics depot

Smart Load Management

80 smart charge points were connected to a central load management platform, enabling dynamic charge scheduling based on fleet departure times, grid import tariffs and on-site generation forecasts. The system reduces peak demand charges while ensuring all vehicles are charged by start of shift.

Site works underway during the EV infrastructure installation
Completed charge point installation at the logistics hub
From DNO application through to energisation of the 80th charge point — a seamless project, delivered exactly to programme.

Logistics Operator Fleet Director

Live and Operational

All 80 charge points were energised and connected to the load management platform within the agreed programme. The grid reinforcement works were completed under a live DNO Section 16 agreement, with no interruption to the existing site supply during construction.